CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Prepare for the CAPM Exam with challenging questions and comprehensive explanations. Utilize flashcards and multiple choice quizzes to enhance your project management knowledge. Ace your exam with confidence!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


Which tool or technique is used in the control communications process?

  1. Cost management systems

  2. Information management systems

  3. Quality auditing

  4. Risk mitigation strategies

The correct answer is: Information management systems

In the control communications process, the tool or technique used is Information Management Systems. This tool helps ensure that information is effectively collected, stored, distributed, and managed throughout the project. Information Management Systems aid in maintaining accurate and timely communication among project stakeholders, which is crucial for the success of the project. Cost management systems (Choice A), quality auditing (Choice C), and risk mitigation strategies (Choice D) are essential tools and techniques used in other project management processes, but they are not specifically related to the control communications process.