CAPM Practice Exam 2025 – Complete Study Resource

Question: 1 / 885

Which is NOT an input of the estimate activity resources process?

Activity cost estimates

Team performance assessments

The estimate activity resources process is a part of the project schedule management knowledge area. This process is primarily concerned with estimating the type and quantities of resources required to complete project activities. Inputs to this process include activity cost estimates, resource calendars, and the schedule management plan.

Team performance assessments are not directly related to estimating activity resources; they are more closely associated with the Manage Team process in the Project Human Resource Management knowledge area. Therefore, B is the correct answer as it is not an input to the estimate activity resources process.

Get further explanation with Examzify DeepDiveBeta

Resource calendars

Schedule management plan

Next Question

Report this question

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy