CAPM Practice Exam 2026 – Complete Study Resource

1 / 885

How is the original estimate technique for finding EAC calculated?

EAC = AC/(BAC - EV)

The original estimate technique for finding EAC is calculated by dividing the actual cost (AC) by the difference between the budget at completion (BAC) and earned value (EV). Option A is the only one that utilizes the concepts of actual cost, budget at completion, and earned value in its calculation. Option B simply adds the actual cost to the budget at completion, which does not accurately reflect the remaining work to be completed. Option C divides the budget at completion by the earned value, which does not consider the actual cost already incurred. Option D subtracts the actual cost from the budget at completion, which does not take into account the earned value or remaining work.

Get further explanation with Examzify DeepDiveBeta

EAC = AC + BAC

EAC = BAC/EV

EAC = BAC - AC

Next Question
Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy