Which of the following is NOT an output of control procurements?

  1. Change requests

  2. Project charter updates

  3. Project docs updates

  4. Work performance info

The correct answer is: Project charter updates

The correct answer is B. Project charter updates. Control Procurements is the process of managing procurement relationships, monitoring contract performance, and making changes and corrections as needed. Outputs of this process typically include change requests, project documents updates, and work performance information. Project charter updates do not typically result from the Control Procurements process as changes to the project charter are usually managed through the Perform Integrated Change Control process, not through Control Procurements.