Which of the following is NOT a stage in Tuckman's team stages?

  1. Forming

  2. Storming

  3. Adjusting

  4. Adjourning

The correct answer is: Adjusting

Tuckman's team stages are a widely recognized group development model, which includes four stages forming, storming, norming, and performing. In this model, Adjusting is not a recognized stage. Instead, the correct last stage in Tuckman's team stages is Adjourning, which refers to the process of wrapping up work and acknowledging the accomplishments of the team. Therefore, option C is incorrect because it is not a stage in Tuckman's team stages.