Which of the following are inputs of define activities?

  1. Project charter and team assignments

  2. Schedule management plan, scope baseline, enterprise env factors, org process assets

  3. Cost management plan and quality metrics

  4. Human resource plan and stakeholder register

The correct answer is: Schedule management plan, scope baseline, enterprise env factors, org process assets

Inputs to define activities include the scope baseline which consists of the project scope statement, WBS, and WBS dictionary. The schedule management plan is also an input, which includes information on activity lists, activity attributes, and activity sequencing. Additionally, the enterprise environmental factors and organizational process assets are necessary inputs as they provide information on external factors and internal procedures that may impact activity definitions. The project charter and team assignments, cost management plan, human resource plan, and stakeholder register are not inputs to define activities and therefore are not correct choices.