Which is NOT an input of the estimate activity resources process?

  1. Activity cost estimates

  2. Team performance assessments

  3. Resource calendars

  4. Schedule management plan

The correct answer is: Team performance assessments

The estimate activity resources process is a part of the project schedule management knowledge area. This process is primarily concerned with estimating the type and quantities of resources required to complete project activities. Inputs to this process include activity cost estimates, resource calendars, and the schedule management plan. Team performance assessments are not directly related to estimating activity resources; they are more closely associated with the Manage Team process in the Project Human Resource Management knowledge area. Therefore, B is the correct answer as it is not an input to the estimate activity resources process.