What is the role of the project participant?

  1. To manage project budgets

  2. To work as subject matter experts providing various contexts to the project environment

  3. To act as a liaison between the project manager and external stakeholders

  4. To oversee project scope changes

The correct answer is: To work as subject matter experts providing various contexts to the project environment

The role of the project participant is not to manage project budgets (A), as that is typically the responsibility of the project manager. The project participant is not solely responsible for providing context to the project environment (B), as this can also be a responsibility of the project manager. The project participant is not the only person acting as a liaison between the project manager and external stakeholders (C), as this communication can also occur through other team members or project managers. Finally, the role of the project participant does not solely involve overseeing project scope changes (D), as this is often a collaborative effort between the project manager and team members. Therefore, the most accurate description of the role of the project participant is to work as subject matter experts providing various contexts to the project environment.