What is the purpose of process decision program charts?

  1. To map out financial investments over time

  2. To record team meetings and decisions

  3. To understand a goal in relation to the steps for getting to the goal

  4. To analyze the competition and market trends

The correct answer is: To understand a goal in relation to the steps for getting to the goal

Process Decision Program Charts (PDPC) are used to understand a goal in relation to the steps required to achieve that goal. PDPC helps project managers visualize the potential obstacles and risks associated with each step of the project, enabling them to proactively plan for contingencies and mitigate risks. This tool is particularly useful for identifying and addressing potential roadblocks before they impact the project timeline and budget. Therefore, option C is the correct answer as it aligns with the purpose and utility of PDPC in project management.