CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Prepare for the CAPM Exam with challenging questions and comprehensive explanations. Utilize flashcards and multiple choice quizzes to enhance your project management knowledge. Ace your exam with confidence!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


What is the purpose of the risk data quality assessment?

  1. To evaluate the degree to which the risk data is useful for risk management

  2. To categorize the risk into different levels

  3. To assess the urgency of the risk

  4. To update the risk register

The correct answer is: To evaluate the degree to which the risk data is useful for risk management

The purpose of the risk data quality assessment is to evaluate the degree to which the risk data is useful for risk management. This process helps project managers and teams understand the reliability, accuracy, and relevance of the risk data collected. It ensures that the information used for risk management is of high quality, enabling better decision-making and effective mitigation strategies. Option B, C, and D are incorrect because they do not accurately reflect the primary purpose of conducting a risk data quality assessment.