What is the output of identifying stakeholders?

  1. Stakeholder register

  2. Org culture/structure

  3. Lessons learned

  4. Project charter

The correct answer is: Stakeholder register

Identifying stakeholders is part of the project initiation process, where stakeholders are identified and classified according to their level of power, interest and influence in the project. The output of this process is the stakeholder register, which includes a detailed list of stakeholders, their roles and responsibilities, communication preferences and strategies for managing their expectations and engagement throughout the project. Options B, C and D are all important aspects of project management, but they are not the direct output of identifying stakeholders. The organization culture/structure may play a role in how stakeholders are managed, but it is not the result of this specific process. Lessons learned and the project charter are also important project documents, but they are not directly related to identifying stakeholders. Therefore, as identifying stakeholders directly results in the creation of the stakeholder register, A is the correct answer.