What is the critical chain method focused on?

  1. Defining a resource-limited schedule

  2. Identifying project risks

  3. Optimizing the project budget

  4. Engaging stakeholders

The correct answer is: Defining a resource-limited schedule

The critical chain method is focused on defining a resource-limited schedule. This method aims to identify and account for the finite availability of resources in a project, ensuring that the project schedule is realistic and achievable within these constraints. By prioritizing resource allocation and managing dependencies effectively, the critical chain method helps in optimizing the use of resources and maximizing project efficiency. Option B, identifying project risks, although important, is not the primary focus of the critical chain method. Option C, optimizing the project budget, and Option D, engaging stakeholders, are also significant aspects of project management but are not the central focus of the critical chain method.