What is pre-assignment in the context of project team acquisition?

  1. Assigning project tasks based on team members' preferences

  2. Selecting project participants in advance for specific expertise

  3. Assigning team roles based on seniority within the organization

  4. Randomly assigning project tasks to available team members

The correct answer is: Selecting project participants in advance for specific expertise

Pre-assignment in the context of project team acquisition refers to selecting project participants in advance for specific expertise. This means that team members are chosen based on their skills, knowledge, and experience that are required for the project. By pre-assigning individuals with the necessary expertise to the project, it ensures that the project team is well-equipped to handle the tasks and challenges that may arise, ultimately leading to a higher likelihood of project success. Options A, C, and D are incorrect because they do not accurately describe what pre-assignment entails in project team acquisition. Assigning project tasks based on team members' preferences, assigning team roles based on seniority within the organization, or randomly assigning project tasks to available team members do not guarantee that the project team is composed of individuals with the required expertise and qualifications for the project at hand.