What is involved in the manage project team process?

  1. Setting project deadlines

  2. Tracking team member performance

  3. Selecting project tools

  4. Budget allocation

The correct answer is: Tracking team member performance

Managing project team involves tracking team member performance to ensure that everyone is working efficiently and effectively towards the project objectives. This process includes providing feedback, resolving conflicts, and coaching team members as needed to enhance performance and promote project success. Setting project deadlines, selecting project tools, and budget allocation are activities that are typically associated with other project management processes, such as developing the project schedule, determining project resources, and managing project costs.