What is included in the org process assets updates from manage stakeholder engagement?

  1. Stakeholder engagement plan

  2. Feedback from stakeholders

  3. Work performance data

  4. Expert judgment

The correct answer is: Feedback from stakeholders

Manage stakeholder engagement is a continuous process that involves identifying, analyzing, and engaging stakeholders throughout the project lifecycle. This process can result in updates to the organization's process assets, which are any artifacts, knowledge, or tools that can be used to perform a project. The process assets updates from manage stakeholder engagement include feedback from stakeholders, as it provides valuable insights and information to improve stakeholder engagement and project performance. Feedback from stakeholders is essential in identifying and addressing issues and concerns, as well as improving communication and collaboration among stakeholders. The other options are incorrect because they are either inputs to the manage stakeholder engagement process (stakeholder engagement plan) or outputs of this process (work performance data and expert judgment).