What is fast tracking in project management?

  1. Reducing project costs by cutting non-essential tasks

  2. Increasing the project team to speed up task completion

  3. Overlapping or performing in parallel activities that would have been done sequentially

  4. Applying additional resources to critical path activities

The correct answer is: Overlapping or performing in parallel activities that would have been done sequentially

Fast tracking in project management involves overlapping or performing activities in parallel that would normally be done sequentially. Options A, B, and D focus on specific methods of reducing project timelines and increasing efficiency, but they do not necessarily involve the same level of overlapping or parallel activities as in fast tracking. Additionally, option B focuses on increasing the project team, which may not always be necessary in fast tracking. Option C is the most accurate because it directly mentions the overlapping or parallel activities involved in fast tracking. Therefore, option C is the correct answer.