What is an output of plan schedule management?

  1. Schedule management plan

  2. Project schedule

  3. Resource leveling plan

  4. Risk management plan

The correct answer is: Schedule management plan

The correct answer is A. A schedule management plan is an output of the plan schedule management process. This document outlines how the project schedule will be developed, monitored, and controlled. It serves as a guide for the project team on how the schedule will be created and managed throughout the project lifecycle. Options B, C, and D are incorrect because they do not align with the specific output of the plan schedule management process. The project schedule is developed based on the plan created in the schedule management plan, resource leveling plan is related to resource management, and the risk management plan focuses on managing project risks, not the project schedule.