CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Prepare for the CAPM Exam with challenging questions and comprehensive explanations. Utilize flashcards and multiple choice quizzes to enhance your project management knowledge. Ace your exam with confidence!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


What is a resource calendar in project management?

  1. A schedule for project milestones

  2. A calendar that documents when team members can work on a project

  3. A tool to track resource costs

  4. A graphical representation of task durations

The correct answer is: A calendar that documents when team members can work on a project

A resource calendar in project management is a calendar that documents when team members are available to work on a project. It helps project managers schedule tasks and allocate resources effectively by providing visibility into the availability of team members. By knowing when each team member is available, project managers can assign tasks appropriately and ensure that the project progresses smoothly. The other options are not correct as they do not accurately describe the purpose or function of a resource calendar in project management.