What is a primary focus of the develop project team process?

  1. Reducing project costs

  2. Increasing project duration

  3. Getting the most out of the project team

  4. Minimizing resource needs

The correct answer is: Getting the most out of the project team

The primary focus of the develop project team process is to get the most out of the project team. This involves developing and enhancing the skills, knowledge, and competencies of team members in order for them to effectively contribute to the project's success. Options A, B, and D are all incorrect because they do not align with the main purpose of this process. While reducing project costs and minimizing resource needs may be beneficial outcomes, they are not the main focus of this process. Increasing project duration also does not fit with the goal of optimizing the project team.