CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Prepare for the CAPM Exam with challenging questions and comprehensive explanations. Utilize flashcards and multiple choice quizzes to enhance your project management knowledge. Ace your exam with confidence!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


What can be modified by the contract change control system?

  1. Only the project schedule

  2. The procurement process

  3. The project’s scope statement

  4. Work performance data

The correct answer is: The procurement process

The contract change control system is primarily concerned with managing changes to the project's procurement processes, such as changes in contract terms, conditions, or requirements. This system ensures that any modifications to the procurement process are properly documented, approved, and implemented in accordance with the contract. Therefore, the correct answer is B. Option A is incorrect because the contract change control system is not limited to only the project schedule. Options C and D are incorrect as the contract change control system does not typically directly modify the project's scope statement or work performance data.