What are the outputs of the control scope process?

  1. Variance reports

  2. Work performance info and change requests

  3. Budget forecasts

  4. Schedule forecasts

The correct answer is: Work performance info and change requests

The control scope process involves monitoring the progress of the project and managing any changes to the scope. Therefore, the outputs of this process are work performance information and change requests. Variance reports (choice A) are typically associated with the control cost process and are used to track and compare actual project costs to the budgeted costs. Budget forecasts (choice C) relate to the control cost process as well, and are used to estimate the final cost of the project based on current performance. Schedule forecasts (choice D) are outputs from the control schedule process, which involves monitoring and adjusting the project schedule to ensure timely completion.