What is the primary process whereby the project management plan is put into action?

  1. Monitor and control project work

  2. Direct and manage project work

  3. Plan project management

  4. Develop project charter

The correct answer is: Direct and manage project work

The other options are incorrect because A: Monitor and control project work is one of the processes involved in project integration management and is focused on keeping the project on track and identifying any issues or changes that need to be addressed. It is not the primary process for putting the project management plan into action. C: Plan project management involves creating the project management plan and determining the necessary processes and tools for managing the project. It is not the primary process for implementing the project management plan. D: Develop project charter is the process of creating the document that formally authorizes the project and gives the project manager the authority to use organizational resources for the project. It is an initial step in project initiation, but it is not the primary process for putting the project management plan into action.