What are the tools and techniques of manage stakeholder engagement?

  1. Communication methods, interpersonal skills, management skills

  2. Information management systems, expert judgment, meetings

  3. Work performance data, issue logs

  4. Change requests, org process assets updates

The correct answer is: Communication methods, interpersonal skills, management skills

Communication methods, interpersonal skills, and management skills are all tools and techniques used to manage stakeholder engagement. These options allow project managers to effectively communicate with stakeholders, build and maintain relationships, and effectively manage any potential conflicts or concerns that may arise. Meeting and information management systems may also be useful, but they are not the primary tools and techniques for managing stakeholder engagement. Work performance data and issue logs are tools used for monitoring and controlling project performance, while change requests and org process assets updates are used for making changes to project plans and processes. Therefore, A is the most comprehensive and accurate answer.