What are the 4 processes of project human resource management?

  1. Plan Human Resource Management, Acquire Project Team, Develop Project Team, Manage Project Team

  2. Organize Human Resource Management, Form Project Team, Lead Project Team, Evaluate Project Team

  3. Establish Project Team, Train Project Team, Supervise Project Team, Disband Project Team

  4. Identify Project Team, Build Project Team, Guide Project Team, Review Project Team

The correct answer is: Plan Human Resource Management, Acquire Project Team, Develop Project Team, Manage Project Team

The correct answer is A. The four processes of project human resource management are Plan Human Resource Management, Acquire Project Team, Develop Project Team, and Manage Project Team. In the project human resource management knowledge area, it is essential to first plan how the human resources will be managed on the project (Plan Human Resource Management). After that, the project team needs to be acquired (Acquire Project Team), which involves selecting and assigning the appropriate resources to the project. Then, it is important to develop the project team (Develop Project Team) by enhancing their competencies and interactions. Finally, the project team must be managed effectively throughout the project lifecycle (Manage Project Team) to ensure the project's success. The other options are incorrect because they do not accurately represent the four processes of project human resource management as defined in the PMBOK Guide.